Evonik/Siemens to test new electrolyser for green hydrogen in Germany
German chemicals firm Evonik is investing in a pilot electrolyser at its site in Herne (Germany) to produce green hydrogen as a starting product for isophorone diamine (IPDA), a key raw material for rotor blades for wind turbines.
In an accompanying project, Siemens Energy is researching how this new electrolysis technology stands up in industrial use. The project consortium started at the end of 2022 and runs until mid-2025.
Both the investment and the research project receive funding from the Federal Ministry of Education and Research. Judith Pirscher, State Secretary at the Federal Ministry of Education and Research (BMBF): “Green hydrogen is the missing piece in the energy transition puzzle. By funding the H2annibal project, we are supporting research into innovative hydrogen technologies in real conditions in a chemical plant. In this way, we are speeding up the transfer from science to industry and supporting the ramp-up of the hydrogen economy in Germany. The Federal Ministry of Education and Research is providing total funding of around EUR9.3 million for these two projects.”
Maike Schuh, CFO of Evonik: “We are investing massively in green growth to position ourselves more sustainably. To reduce our carbon footprint, we intend to invest a total of EUR700 million in production processes and infrastructure group-wide by 2030. Hydrogen electrolysis in Herne is a key element in that.”
Evonik and Siemens Energy are therefore driving forward the industrial transformation in the area of climate protection precisely where the Hannibal mine extracted hard coal until about 50 years ago.
Rainer Stahl, manager of the Herne site: “In the H2annibal project, we are testing a new type of electrolysis technology and therefore making a contribution to reducing CO2emissions and, at the same time, safeguarding the sustainable supply of hydrogen and oxygen to our production facilities in the mid-term.”
At present, the hydrogen used by Evonik in Herne is fossil-based. In the future, green hydrogen should be produced directly at this site using a PEM (proton exchange membrane) electrolyser from Siemens Energy with rated power of 8 MW. This will be operated with renewable energy.
Green hydrogen from this electrolyser could meet up to 45% of the hydrogen and, in addition, 100% of the oxygen required at this site. In the electrolysis process, water is split into hydrogen and oxygen with the aid of electricity.
Using the electrolyser could avoid 12,000 metric tonnes CO2 a year.
Manuel Mundt, Vice President Finance for Sustainable Energy Systems at Siemens Energy: “Avoiding greenhouse gas emissions is particularly difficult in the industrial sector. We need innovations and strong partnerships to find new technological routes that drive forward the transformation of industry.”
In Herne, Evonik and Siemens Energy now have an opportunity to test a new generation of the electrolysis system for green hydrogen in a complex integrated production system that is typical for the chemical industry. Herne is a model for a chemical park with fluctuating, demand-driven hydrogen requirements.